DUE DILIGENCE
Turbine due diligence: the checklist
Before money moves on a used turbine: borescope report (hot-section condition — blades, combustor, nozzles; the single most important document), hours and starts (both — peaker duty is cycle-heavy and cycles drive maintenance intervals), OEM service history (GE, Siemens, or qualified independent — what was done, when, by whom), remaining life assessment (hot-section life remaining in hours/starts before the next major), controls version (obsolete control systems can cost more to upgrade than the turbine), and what conveys (auxiliaries, inlet/exhaust, generator, switchgear — the turbine without its package is a project). Turbine deals die on missing paperwork, not on price — the informed buyer’s first request is always the records.