01Size the service and do the load calculation
Start with NEC Article 220: calculate the general lighting load (3 VA per square foot), add small-appliance and laundry circuits, then major appliances at nameplate. Most modern homes land on a 200-amp service, but the calculation — not habit — decides. Undersizing the service is the most expensive mistake in residential wiring because fixing it means doing the service twice.
02Draw the circuit map
Lay out every circuit on paper: lighting per room, receptacle circuits, dedicated runs for the fridge, microwave, dishwasher, disposal, washer, dryer, range, water heater, and HVAC. Note breaker size and wire gauge for each. A complete map lets you buy wire once, pull in a logical order, and hand the inspector a panel schedule that matches reality.
03Rough in the boxes first
Mount every box before pulling a single cable: receptacles 12 to 16 inches off the floor, switches 48 inches, all at consistent heights. Keep boxes flush with the finished wall surface — boxes set too deep fail inspection and make device trim miserable. Size each box for fill per NEC 314.16: count conductors, devices, and clamps, and use the volume allowances in the table.
04Pull cable in a logical order
Pull home runs back to the panel first, then daisy-chain devices. Drill holes through the center of studs and keep cable at least 1-1/4 inches from the stud edge — closer than that requires a steel nail plate (NEC 300.4). Staple NM cable within 12 inches of every box and at least every 4-1/2 feet along the run (NEC 334.30). Leave 8 inches of conductor at each box for device connections.
05Wire for the inspection, not just for power
The rough-in inspection happens before drywall, and the inspector is checking the details: proper stapling, nail plates where required, cable protected through bored holes, boxes set correctly, and grounding conductors made up. Neat, consistent work passes; sloppy work gets flagged circuit by circuit. Label every home run at the panel end as you pull it.
06Make up the panel with care
Land the grounding electrode conductors first, then neutrals on the neutral bar and grounds on the ground bar (bonded together only in the main service panel — NEC 250.24). Route conductors neatly, leave service loops, and torque every terminal to the manufacturer's specification — NEC 110.14(D) made torque a code requirement because loose connections start fires. Label every breaker on the panel directory (NEC 408.4).
07Trim out devices after paint
Install receptacles, switches, and fixtures only after drywall and paint are done. Wrap device screws with the conductor clockwise so tightening pulls the wire in, not out. Test every device with a receptacle tester: correct wiring, proper ground, and GFCI/AFCI function where required. Fix anything the tester flags before the final inspection.
08Walk the final inspection like the inspector
Before the inspector arrives, walk every room with your circuit map: test each receptacle, flip each switch, trip and reset each GFCI and AFCI. Confirm the panel directory matches the breakers, all cover plates are on, and smoke and CO detectors are in place per local code. A house that is pre-walked passes the first time; a house that is not gets a correction list.