01Start from the drawings and the load calc
Review the engineered one-lines, panel schedules, and lighting plans before anything else — commercial work builds to the drawings. Verify the service size against the NEC 220 commercial load calculation: lighting loads by occupancy type, receptacle loads, HVAC equipment, and specialty loads, with continuous loads at 125%. If the drawings and the calculation disagree, resolve it with the engineer before rough-in, not during inspection.
02Build the distribution: service to panels
Install the service equipment, distribution panels, and subpanels per the one-line: service-entrance conductors sized per 230, grounding electrode system per 250, and each panelboard landed with neutrals and grounds correctly separated or bonded per its position in the system. Commercial distribution often includes multiple voltage systems (480/277 for lighting and HVAC, 208/120 for receptacles) — keep them straight, label everything, and verify phasing.
03Choose raceway by location and drawing
EMT for exposed work and most concealed commercial runs (NEC 358), MC cable where the drawings and local code permit it, cable tray (NEC 392) for long horizontal distribution above ceilings. Each wiring method has its own support, fill, and bending rules — and its own labor profile. The cheapest raceway on paper is not the cheapest installed; bid the method, not just the material.
04Rough in branch circuits systematically
Pull branch circuits zone by zone, labeling every home run at both ends as you go. Commercial receptacle layouts follow the drawings exactly — spacing, dedicated circuits for copiers and kitchenettes, isolated grounds where specified. Keep lighting and receptacle circuits on their scheduled panels; cross-connecting panels turns the panel schedule into fiction and the troubleshooting into archaeology.
05Wire the lighting and controls per plan
Install fixtures per the reflected ceiling plan, with the specified controls: occupancy sensors, vacancy sensors, daylight harvesting, and timeclocks per the energy code. Emergency egress lighting and exit signs get their own circuits per NEC 700 — they are life-safety systems with dedicated inspection. Test every control sequence functionally, not just electrically: the sensor must actually turn the lights off.
06Land panels with documentation discipline
Terminate every panel with the directory filled out completely and accurately — commercial panel schedules are legal documents that the facilities team will use for decades. Torque all terminations to spec (NEC 110.14(D)), verify neutral-ground bonding only at the service, and confirm breaker sizes match the schedules. A commercial panel that is neat, torqued, and correctly labeled passes inspection and earns the next contract.
07Test systematically before inspection
Test in layers: continuity and insulation resistance on feeders, voltage and phasing at each panel, every branch circuit under load, GFCI and AFCI function where required, emergency lighting transfer tests, and fire alarm interface verification. Document the results — commercial inspectors expect test records, and the commissioning agent will want them too. Finding your own problems before the inspector does is the whole game.
08Close out with as-builts
Deliver as-built drawings showing what was actually installed, updated panel schedules matching the directories, and the test records. Walk the facilities manager through the distribution: where the panels are, what they serve, where the disconnects live. A commercial buildout is not done when the lights turn on — it is done when the next electrician can understand it from your paperwork.
09Coordinate the other trades early
Electrical rough-in collides with mechanical, plumbing, and fire protection in every ceiling — the trade that coordinates wins and the trade that does not reworks. Attend the coordination meetings, stake your sleeve and opening locations on the drawings, and walk the ceiling with the mechanical foreman before you pull a single run. Agree on elevation zones: whose duct, pipe, tray, and conduit lives at which height. An hour of coordination saves a week of moving conduit around someone else's ductwork.